Answer these PMP®/CAPM® questions depicted by these pictures
Click on the picture to enlarge it !
one
Highlight between brackets to see the answer:
Answer: (Not stable.Rule of 7)
two
Answer: (Balanced Matrix)
three
Answer: (Projectized organization)
four
Answer: (A is Contingency Reserve,B is Management Reserve)
five
Types of Cost Estimates
Answer: (A is -25% to +75%,B is Budgetary estimate,C is -5% to +10%)
six
Answer: (1=Tick,2=X,3=X,4=X)
seven
Answer: (B. Low Grade is acceptable but not low Quality)
eight
Answer: (Project coordinator has more power than Project Expediter)
nine
Answer: (Lag )
ten
Answer: (CCM - Critical Chain Method has project buffer,feeding buffer, Resource buffer)
Read next:
Picture Question 2
Picture Question 2
No comments:
Post a Comment