"“A clay pot sitting in the sun will always be a clay pot. It has to go through the white heat of the furnace to become porcelain.” - Mildred Struven
Showing posts with label picture question. Show all posts
Showing posts with label picture question. Show all posts

PMP®:CAPM® - CPM Questions & Answers

Check out Critical Path Method to answer these questions.
http://vc4u.blogspot.in/2016/01/pmpcapm-critical-path-method-cpm.html

Q1. CPM:
PMP:CAPM - CPM Question
Q1. CPM Answer:
PMP:CAPM - CPM Answer
Q2. CPM:

Q2. CPM Answer:

Q3. CPM:

Q3. CPM Answer:

Q4. Find the Free Float & Total Float:

PMP:CAPM - Free Float & Total Float question 1
Q4. Free Float & Total Float Answer:
PMP:CAPM - Free Float & Total Float answer 1
Q5. Find the Free Float & Total Float:
PMP:CAPM - Free Float & Total Float question 2
Q5. Free Float & Total Float Answer:
PMP:CAPM - Free Float & Total Float answer 1

PMP®:CAPM® - Picture Questions 3

PMP:CAPM - Picture questions 3

Answer these PMP®/CAPM® questions depicted by these pictures

Click on the picture to enlarge it !

one


Highlight between brackets to see the answer:
Answer: (PMO-Project Management Office)
two 
PMP:CAPM - 7 Quality management tools

Answer: (Affinity Diagram,Activity Network Diagram,Tree Diagram)
three
PMP:CAPM-Cost of Quality

Answer: (Appraisal cost & Internal Failure Cost)
four
PMP:CAPM - ? management plan

Answer: (Staffing management plan)
five
PMP:CAPM - EEF or OPA



Answer: (Enterprise Environmental Factors )
six
PMP:CAPM-OPM3

Answer: (M1-Management,M2-Maturity,M3-Model)
seven
PMP:CAPM-Plans and Baselines


Answer: (Project Management Plan)
eight
PMP:CAPM-Procurement match quiz

Answer: (1-B,2-C,3-A,4-D)
nine
PMP:CAPM - Perform Quality Assurance


Answer: (Execution Process Group)
ten
PMP:CAPM-Risk management picture question

Answer: (A-Quantitative , B - Tornado, C - Sensitivity)



PMP®:CAPM® - Picture Questions 2


Answer these PMP®/CAPM® questions depicted by these pictures

Click on the picture to enlarge it !

one
Control Chart

Highlight between brackets to see the answer:
Answer: (Blues are due to random or common causes.Reds are due to special causes   or assignable causes)
two 

Answer: (Accountable)
three

Answer: (3 & 5)
four

Answer: (B is true. Stakeholders need not be shareholders for e.g public)
five



Answer: (Collaboration, Avoiding, Reconcile, Forcing, Accommodating )
six

Answer: (Work Performance)
seven


Answer: (Monitor)
eight

Answer: (Legitimacy)
nine


Answer: (Accept,Escalate)
ten

Answer: (A - 2,5. B-4, C-1,6. D-3. E-7)

Read next:

PMP®:CAPM® - Picture Questions 1


Answer these PMP®/CAPM® questions depicted by these pictures

Click on the picture to enlarge it !

one

Highlight between brackets to see the answer:
Answer: (Not stable.Rule of 7)
two 

Answer: (Balanced Matrix)
three

Answer: (Projectized organization)
four

Answer: (A is Contingency Reserve,B is Management Reserve)
five
Types of Cost Estimates



Answer: (A is -25% to +75%,B is Budgetary estimate,C is -5% to +10%)
six

Answer: (1=Tick,2=X,3=X,4=X)
seven


Answer: (B. Low Grade is acceptable but not low Quality)
eight

Answer: (Project coordinator has more power than Project Expediter)
nine


Answer: (Lag )
ten

Answer: (CCM - Critical Chain Method has project buffer,feeding buffer, Resource buffer)

Read next:
Picture Question 2