PMP® Tricky Questions
These Questions were compiled from the 'I want to be a PMP®' Linkedin group. The answers are not given purposely. Click on the question to see it bigger.
1
Ans D. VAC=12500, BAC=75000,ETC=15750. VAC=BAC-EAC,
So EAC = BAC-VAC=75000-12500=62500.
EAC=AC+ETC. AC=EAC-ETC=62500-15750=46750
2
Ans C. ETC=1000,000,AC=1200,000.
EAC=AC+ETC=1200,000+1000,000 =2,200,000
3
Ans C. Crashing compressed the schedule but increased the cost
4
Ans D. Depreciation is a non cash expense
5
Ans D. Underestimation will influence the future EAC= BAC/CPI
PV= $1,200,000, EV= $1,000,000, AC= $1,200,000
BAC - EV = $1,000,000
BAC - EV = 1,000,000 ,BAC = EV + 1,000,000 = 2,000,000.
CPI=EV/AC= 1,000,000/1,200,000 = 1/1.2
EAC= BAC/CPI = 2,000,000x1.2 = 2,400,000
6
Ans A. Remaining work is BAC-EV
ETC = AC + (BAC-EV)=BAC - (EV-AC)=BAC - CV
7
Ans C. Variance is atypical. So EAC=AC+(BAC-EV). ETC=BAC-EV=40000-8000=32000
8
Ans B. cost baseline = estimate + contingency reserve
9
Ans A. Budgetery estimate range is -10% to +25%. So it should not cross 125000
10
Ans C. Since Question mentions external stakeholder and agreement answer is Conduct procurements
11
Ans A. Scope validation is not only performed while the project is executing - it is also performed when a project is terminated. It is used to determine the level of completion.
12
Ans D. Any change should always be
analyzed for its impact scope, cost, and schedule and change request to be raised.
13
Ans C. This is about the Collect requirements process
14
Ans D. Rolling Wave planning is a form of Progressive elaboration planning. In this technique project team plans for the near future as detailed as possible, while the work far in the future remains planned on a high level.
15
Ans B. In Strong matrix the PM keeps the Functional Manager in loop
16
136. 10 communication channels means 5 members in Bengaluru. Total no. of members = 5+7+5. n is 17. no. of channels = (17*16)/2
17
Ans C. This will help in knowing about each others culture
18
Ans A. Infrastructure is part of EEF. Communication technology tools are part of infrastructure
19
Ans B. Personally you can talk with 4 people i.e. 4 channels
20
Ans B. You would have already done this in Validate scope
21
22
Ans D. Project management doesn't have other options. It has the subsididary plans and the 3 baselines(Cost,Schedule,Scope)
23
Ans C. If a dispute is not resolved between the parties, it need to be settled by ADR(Alternate Dispute Resolution i.e. dispute resolution by neutral third party)
24
Ans B. Lessons learnt help in all other options
25
Ans D. A contract should be legally binding. Violating law of land is not legally binding
26
Ans C. Time and material is a hybrid contract, generally used in IT environment and where scope is changing and not fixed. It carries less cost risks than Cost plus contracts.
27
Ans D. Repeated measurements are close to one another but not close to the actual value. Hence precise but not accurate
28
Ans A. We normally don't do any response planning for this risk
29
Ans B. EMV is based on risk neutral assumption. Others are false.EMV is a quantitative technique not qualitative
30
Ans D. changes related to the current project need to be done on the risk checklist
31
Ans C. option C is procurement related others are risk related
32
Ans B. providing cross training will help a backup person take care if one person resigns
33
Ans B. subcontracting is transferring the risk to a third party
34
Ans D. Only the lowest level are work packages not all levels
35
Ans A. Collect requirements from stakeholders will improve their active participation, which will lead to least changes later on, leading to timely closure n success of project
36
Ans B
37
Ans 11 days
38
Ans C. add the durations, for SD average, sqrt ( sum of square of the SDs)
39
Answer is 21.ABEG is the critical path
40
Answer is B. 15+(15*(10/100)) gives 17 after rounding. (10+4*17+30)/6=18
41
Answer is B. 15+(15*(10/100)) gives 17 after rounding. (10+4*17+30)/6=18